SAP Project Manager C_PM_71 certification exam is organized in a systematic way in the C_PM_71 practice test software so that you cover all the key areas within short time quickly. SAP C_PM_71 exam dumps simulation makes the learning easier and quicker and facilitates you in customizable learning as well. You can learn how to complete the SAP C_PM_71 exam in time by managing time according to the C_PM_71 exam pattern.

C_PM_71 PDF dumps; C_PM_71 exam dumps:: https://www.dumpsschool.com/C_PM_71-exam-dumps.html (94 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate SAP C_PM_71 Dumps Exam Questions and Answers:

Version: 4.0
Question: 21

What tasks in the Business Blueprint phase do you execute to define the Organizational Change Management (OCM) Communication plan?
There are 2 correct answers to this question.
Response:

A. Define Project Organization
B. Define Communication Strategy
C. Define value argumentation and key messages
D. Refine Acceptance Criteria

Answer: BC

Question: 22

Youre a project manager in a large implementation project that is just about to start transitioning to the production environment.
Your order management team indicates that several warehouse employees do not seem ready to go live.
Youre unsure if you should proceed with the go live activities as planned.
What Organizational Change Management (OCM) Deliverable do you use to assess wither the organization is ready to go live and the new system?
Response:

A. OCM Road show
B. Pre go live end-user training
C. Production cut over
D. Organizational and Production Support Readiness Check

Answer: B

Question: 23

New Updated C_PM_71 Exam Questions C_PM_71 PDF dumps C_PM_71 practice exam dumps: https://www.dumpsschool.com/C_PM_71-exam-dumps.html

Which of the following must be included in the project charter?
Please choose the correct answer.
Response:

A. Project organizational chart
B. Project objectives and benefits
C. Project team training plan
D. Solution architecture diagram

Answer: B

Question: 24

Which of the following tasks need to be completed successfully to complete the production cutover deliverable?
There are 3 correct answers to this question.
Response:

A. Obtain Production Data Sign-off
B. Finalize Cutover plan
C. Conduct Project Management Review Service
D. Execute Multiple cutover Simulations
E. Preform people readiness assessment

Answer: BDE

Question: 25

Which Accelerators from the ASAP Roadmap do you leverage to complete the Phase Closure and Sign-off Phase Deliverables?
There are 2 correct answers to this question.
Response:

A. Project Quality Gate Scorecard Template
B. Project Setup Check list Sample
C. Phase Closure Report Template
D. On-Boarding Template

Answer: AC

Question: 26

In the Project Preparation phase Data Quality Analysis in initiated.
Which Accelerators in the Data Migration Approach and Strategy deliverable is used to capture the baseline for Data Quality?
Response:

A. Data Migration Workshop Findings Template
B. Data Migration Approach and Strategy Template
C. Data Audit Results Report Template
D. Data Migration Scoping Questionnaire Template

Answer: C